How is the predetermined overhead allocation rate used to allocate overhead?

Ralph’s Machine Tools Company assigns manufacturing overhead costs based on direct labor and applies this rate to job orders.

Ralph’s Machine Tools Company had an estimated manufacturing overhead cost of $15,000 for the upcoming year.

The direct labor hours it expects for the upcoming year are 2,000.

This information can be used to calculate the predetermined overhead rate.

Estimated manufacturing overhead cost/Estimated total units in the allocation base = Predetermined overhead rate

The predetermined overhead rate for Ralph’s Machine Tools Company is:

$15,000/2,000 hours = $7.50 per direct labor hour.

The formula used to compute the predetermined overhead rate uses estimates.

This means that the overhead that is applied to jobs or products is different than the actual overhead from the product or job.

The adjustment made to eliminate this difference at the end of the period is called the disposition of over or underapplied overhead.

Example 2

Dorothy’s Hat Company computed a predetermined overhead rate based on annual machine hours.

At the start of 2021, Dorothy’s Hat Company estimated that the total manufacturing overhead cost for the year would be $320,000, and the total machine hours would be 50,000 hours.

The company actually had $300,000 in total manufacturing overhead costs for the year, and the actual machine hours used were 53,000.

Now, compute the predetermined overhead rate for 2021.

Determine the manufacturing overhead costs that Dorothy should have applied to her hats.

Answer

Predetermined overhead rate:

Estimated manufacturing overhead cost/Estimated machine hours

$320,000/50,000 hours = $6.40 per machine hour

Manufacturing overhead applied to products:

Actual machine hours used x Predetermined overhead rate

53,000 * $6.40 = $339,200

Example 3

The operating and cost data are given next for three separate companies.

The companies use different allocation bases when calculating their predetermined overhead rates.

Company 1Company 2Company 3Direct Labor Hours95,000120,000150,000Machine Hours140,00080,000110,000Direct Materials Cost$800,000$600,000$900,000Manufacturing Overhead Cost$1,000,000$860,000$1,110,000

Company 1: Machine hours

Company 2: Direct materials cost

Company 3: Direct labor hours

Next, calculate the predetermined overhead rate for the three companies above.

Answer

Company 1

Estimated manufacturing overhead cost/Estimated machine hours

$1,000,000/140,000 hours = $7.14

Company 2

Estimated manufacturing overhead cost/Estimated direct materials cost

$860,000/$600,000 = $1.43

Company 3

Estimated manufacturing overhead cost/Estimated direct labor hours

$1,110,000/150,000 = $7.40

Multiple Predetermined Overhead Rates

The predetermined overhead rate as calculated above is a plant-wide overhead rate or a single predetermined overhead rate.

This rate is generally only used by small companies.

Large companies will typically have a predetermined overhead rate for each production department.

Using multiple predetermined overhead rates is more complicated and takes more time, but it is generally thought to be more accurate than using a single predetermined overhead rate for the entire plant.

Example 4

The Holiday Candy Company uses a job-order costing system and calculates different predetermined overhead rates for its molding and packaging departments.

These are the estimates the company computed at the start of 2021.

Molding Department

Direct labor hours: 5,000

Machine hours: 25,000

Manufacturing overhead cost: $150,000

Direct labor cost: $50,000

Packaging Department

Direct labor hours: 24,000

Machine hours: 7,000

Manufacturing overhead cost: $528,000

Direct labor cost: $240,000

The molding department bases its overhead rate on its machine hours. Whereas the packaging department bases its overhead rate on labor hours.

Now, calculate the predetermined overhead rate for the departments listed above.

Answer

Molding Department

The overhead rate for the molding department is computed by taking the estimated manufacturing overhead cost and dividing it by the estimated machine hours.

Overhead rate for the molding department = estimated manufacturing overhead cost/ estimated machine hours

$150,000/25,000 hours = $6 per machine hour

The overhead rate for the molding department is $6 per machine hour.

Packaging Department

The overhead rate for the packaging department is calculated by taking the estimated manufacturing overhead cost and dividing it by the estimated direct labor cost.

Estimated overhead for the finishing department = estimated manufacturing overhead cost/ estimated direct labor cost

$528,000/$240,000 = $2.20 per dollar of direct labor

The overhead rate for the packaging department is $2.20 per dollar of direct labor.

This means the manufacturing overhead cost would be applied at 220% of the company’s direct labor cost.

Article Sources & Citations

FundsNet requires Contributors, Writers and Authors to use Primary Sources to source and cite their work. These Sources include White Papers, Government Information & Data, Original Reporting and Interviews from Industry Experts. Reputable Publishers are also sourced and cited where appropriate. Learn more about the standards we follow in producing Accurate, Unbiased and Researched Content in our editorial policy.

What is the predetermined overhead rate and why is it used?

What is a Predetermined Overhead Rate? A predetermined overhead rate is an allocation rate that is used to apply the estimated cost of manufacturing overhead to cost objects for a specific reporting period.

Why are predetermined overhead rates used at the beginning of the year?

Typically, companies use this rate to close the books more quickly. The rate avoids collecting actual manufacturing overhead costs as part of the closing period. Note: an accountant must determine the difference between the estimated and actual amounts of overhead by the end of each fiscal year.

Chủ Đề